WUV Dam Removal Design and Implementation Block Grant Closes with 14 Dams Removed!

Vermont has hundreds of “deadbeat” dams, many of which no longer serve their historic purpose and pose a threat to water quality, wildlife, and public safety. Organizations across Vermont work to design and implement these complex dam removal projects to improve water quality, habitat connectivity, and flood resilience in our rivers.  In 2022, Watersheds United Vermont (WUV), a nonprofit organization focused on supporting community-based watershed groups to protect and restore Vermont’s waters, received the Dam Removal Design and Implementation Block Grant from the Vermont Department of Environmental Conservation’s (DEC) Clean Water Initiative Program (CWIP) to subgrant funds to project implementers to complete  dam removal projects throughout Vermont. The focus of the Dam Removal Design and Implementation Block Grant (Dam Removal DIBG) program was to support projects that reduce sediment and nutrient pollution, including phosphorus, from runoff and soil erosion that discharge into the State’s rivers. The projects also have numerous co-benefits including flood resilience, aquatic organism passage and aquatic and riparian habitat improvements.

In November 2026, WUV and DEC closed out the current Dam Removal Design and Implementation Block Grant. WUV and DEC continue to support dam removal projects through an active Enhancement Dam Removal Design and Implementation Block Grant that goes through 2030. Over the 4 year period of the Dam Removal DIBG, WUV subgranted $2,079,780  to fund a total of 22 projects across the state of Vermont. Watersheds United Vermont provided grant funds to non-profit watershed groups, Natural Resources Conservation Districts, Regional Planning Commissions, land trusts, municipalities, and other conservation organizations working to remove dams across Vermont. As a result, these dedicated project implementers completed 4 preliminary design projects and 9 final design projects, serving as the basis for the future dam removal implementation projects. In many cases, these design projects have already moved to the next stage of design or have been (or are in the process of being) implemented. Subgrantees also completed 14 implementation projects removing 14 dams across Vermont. The environmental benefits resulting from the implementation projects under this grant include over 4,500 feet of stream restored, 275 acres of floodplain restored and reconnected, and over 35 stream miles reconnected for stream equilibrium/aquatic organism passage.

The following dams were removed by the listed implementing organizations under the Dam Removal DIBG Program (does not include design projects):

Rockefeller Dam, Plymouth VT - Farm and Wilderness Foundation

Cross Brothers Dam, Northfield VT - Town of Northfield

Youngs Dam, West Rutland VT - Town of West Rutland

Simpson Dam, Dorset VT - Vermont Land Trust

Blake Higgins Dam, Westminster VT - Connecticut River Conservancy

Valley Street Dam, Springfield VT - Mount Ascutney Regional Commission

Beaver Brook Dam, Wilmington VT -  Connecticut River Conservancy

Connolly Pond Dam, Shrewsbury VT - Vermont Natural Resources Council 

Jockey Hollow Dam, Barre Town VT - Friends of the Winooski River

Sleeper Pond Dam, Newport Town VT - Missisquoi River Basin Association

Jericho Town Forest Dam, Jericho VT - Town of Jericho 

Farnham Brothers Dam, Tunbridge VT - White River Partnership 

Austin Pond Dam Removal, Hubbardton VT - The Nature Conservancy 

Mountain School Dam, Shrewsbury VT - Rutland Natural Resource Conservation District 

The WUV Dam Removal Design and Implementation Block Grant Funds supported projects across Vermont in the Connecticut, Memphremagog, and Champlain watersheds. This work would not have been possible without the incredible expertise and hard work of our clean water project implementers throughout the state who managed these complex dam removal projects. These subgrantees provide the on the ground expertise, project oversight, and management to design and implement the projects funded under this grant program. Project implementers and work with landowners, engineers, local construction contractors, and partners to make these projects possible and, as a result, these projects help to support environmental restoration jobs across Vermont. This work would also not have been possible without the dedication and expertise of the staff at the Vermont Department of Environmental Conservation. 

While the Dam Removal Design and Implementation Block Grant has come to an end, WUV is  continuing to fund dam removal design and implementation projects through Vermont DEC’s Clean Water Initiative Program under the Enhancement Dam Removal Design and Implementation Block Grant that is providing funding for dam removals projects through 2030. WUV is currently funding 12 dam removal design and implementations projects under this new grant  and will release another Request for Proposals in December with applications due in February 2027. The Enhancement Dam Removal Design and Implementation Block Grant Program focuses on projects that   protect high quality waters, restore stressed and degraded waters, improve watershed resilience, and enhance the public’s use and enjoyment of our waters. 

Please visit WUV’s grant page: https://watershedsunitedvt.org/grants to learn more about the Enhancement Dam Removal Block Grant program.